SPECIFICATIONS

General Specifications

  • 30,000 Square Feet
  • 250 Pounds per Square Foot Floor Loading
  • 12-Foot Ceilings
  • 470-Vehicle Secured, Underground, On-Site Parking
  • Four 7,000-Pound Freight Elevators
  • One 15,000-Pound Freight Elevator

Industry Certifications & Classifications

  • SSAE 16 (SOC1) Certified
  • PCI Compliant

Mechanical

  • Redundant HVAC System
  • More Than 430-Ton Capacity

Electrical

  • 3,000 Amp Utility Service
  • In-Building Utility Substation
  • Dedicated Two Megawatt Diesel Back-Up Generator with 3,000 Gallon Fuel Tank
  • Redundant Uninterruptible Power Supply Systems (UPS) with Maintenance Bypass

Fire Suppression

  • VESDA (Very Early Smoke Detection Apparatus) Air Sampling
  • Dual Zone Pre-Action (Dry Pipe) Fire Suppression

Security

  • Biometric Hand-Geometry Scanners
  • Proximity Card Key Access
  • High Resolution Video Surveillance Throughout with 90-Day Archiving
  • Full 24-Hour Building and Facility Access
  • Secure Storage Available
  • Secured Cabinets and Larger Private Cages Available
  • Video Intercom

Connectivity

  • Existing Connectivity Through Three Diverse Building Risers
  • Additional Building Risers Available
  • Four Building Points of Entry (POE) of Network Providers
  • Access to Diverse Dark Fiber Facilities
  • Meet-Me Facility

Controls & Monitoring

  • On-Site Operations Control Center (NOC-OCC)
  • Cross-Mounted Digital and Analog Management Systems and Software
  • Complete Remote Access for Monitoring
  • Network Monitoring
  • Temperature & Humidity Monitoring
  • Power Monitoring to the Distributed Circuit Level
  • Custom Monitoring Reports Available

We are proud of our facility and would enjoy the opportunity to give you a tour in person.  Please Contact Us to arrange a full tour, but feel free to take the virtual tour in the meantime.

  • The Datotel Risk Assessment Methodology:

    Risk assessments come in many forms, but the underlying purpose is to identify and document known risks to a given process or system and identify the consequences if that risk were to occur. With the risks both identified and quantified, … Continue reading